News & Updates
Construction work for Phases 1 and 2 (see phasing map) of the parking lot at the George DiCiero Building Complex (DMV, Clerk/Recorder, Community Development) is complete. Phase 3 (Police and Court) will resume in Spring 2026.
Construction work at the Outlook Park location is complete. The parking lot is now open to the public.
Construction work at the Depot Museum is anticipated to begin early Summer 2026.
Project Summary
The proposed improvements include new asphalt pavement, ADA accessibility upgrades, sidewalk repairs, and pavement striping. This work is part of the City and County of Broomfield's annual parking lot improvements program.
Work at these parking lots will be performed in a manner that minimizes impact on the public. However, please plan for temporary changes to parking and access during construction.

Background Information
The Parking Lot Repair/Replacement - Citywide Program’s purpose is to improve the asphalt pavement, reconstruct ADA ramps and enhance sidewalk accessibility.
Year 2025 projects included the George Di Ciero Building and Outlook Park, both identified as top priorities for repair. This year, Phase 3 of the GDC parking lot and the Depot Museum lot will be completed. The annual program evaluates and prioritizes parking lots based on remaining service life (RSL) ratings.
The GDC and Outlook Park projects were advertised for bid in June 2025 and bid proposals were received in July, 2025. Denver Dirt Works, Inc. was selected to perform the construction work. The Depot Museum will be advertised for bid early this year.
Contact Us
Elizabeth Racca-Johnson
CIP Project Manager, Community Development