Construction is up all over the metropolitan area so building departments are busy! Please schedule enough time for a plan review to keep your project on track.
Over the counter plan reviews - Not Available - Please submit applications & plans to buildingpermits@broomfield.org -(Basement Finish, Small Remodels, Decks, Pergola's, Patio Covers, and any other permit that requires a plan reviewer)
Typical plan review times are as follows:
New house – custom or new model - 10 to 11 weeks for first comments
New house – a master plan - 10 to 11 weeks for first comments
New house w/approved master plan - 10 to 11 weeks
New commercial – 9 to 10 weeks for first comments
Tenant finish - 7 to 8 weeks for first comments
Residential additions – 4 to 5 weeks for first comments
Residential Remodel / Basement Finish - 3 to 4 weeks
Exterior Residential - decks, covered patios, pergolas, gazebo, etc. - 3 to 4 weeks
Solar PV Systems - 4 to 5 weeks
Signs - 4 to 5 weeks
Windows - 4 to 5 weeks
Water Heaters, Furnaces & A/C's - 7 to 8 days
Re-Roofs - 7 to 8 days
Estimated times above are goals, but are not guaranteed!