Review Timelines

Construction is up all over the metropolitan area so building departments are busy! Please schedule enough time for a plan review to keep your project on track.

Over the counter plan reviews - Not Available - Please submit applications & plans to buildingpermits@broomfield.org -(Basement Finish, Small Remodels, Decks, Pergola's, Patio Covers, and any other permit that requires a plan reviewer) 

Typical plan review times are as follows:

New house – custom or new model - 10 to 11 weeks for first comments  

New house – a master plan - 10 to 11 weeks for first comments

New house w/approved master plan - 10 to 11 weeks

New commercial –  9 to 10 weeks for first comments

Tenant finish - 7 to 8 weeks for first comments

Residential additions – 4 to 5 weeks for first comments 

Residential Remodel / Basement Finish  - 3 to 4 weeks

Exterior Residential - decks, covered patios, pergolas, gazebo, etc. - 3 to 4 weeks

Solar PV Systems - 4 to 5 weeks

Signs - 4 to 5 weeks

Windows - 4 to 5 weeks 

Water Heaters, Furnaces & A/C's - 7 to 8 days

Re-Roofs - 7 to 8 days


Estimated times above are goals, but are not guaranteed!