On Oct. 4, 2019, Xcel Energy pressure tested its lines in the area of the Davis 43-6 plugged and abandoned well.
On Oct. 4, 2019, Xcel Energy pressure tested its lines in the area of the Davis 43-6 plugged and abandoned well, in the area indicated in red on the map linked here. Broomfield has been notified by the Public Utilities Commission, Chief of Pipeline Safety, that all lines in this area passed the pressure test with 100 pounds per square inch readings. Please see the Public Notice for more information on the testing here. This completes Xcel’s testing. ERO, Broomfield’s soil gas testing contractor, has installed deep probes and testing will continue the week of Oct. 6, 2019.