Extraction Oil and Gas has completed the hydraulic fracturing, coiled tubing mill out, and production tubing installation for 10 wells at the Interchange B Pad.
Extraction Oil and Gas has completed the hydraulic fracturing, coiled tubing mill out, and production tubing installation for 10 wells at the Interchange B Pad. The final step of the completions phase of operations for these 10 wells is the flowback of hydraulic fracturing fluids in preparation for putting these wells into production. Per the Operator Agreement, Extraction is required to use pipelines for the flowback fluids to the maximum extent feasible. Presently, the pipeline is scheduled for completion in late September or early October of 2019. Read the newsflash here.