Staff is providing this update to Council and on the oil and gas webpage regarding the status of Livingston pad construction.
Staff is providing this update to Council and on the oil and gas webpage regarding the status of Livingston pad construction. Extraction is currently in the process of constructing the access drive for the Livingston Pad Site in Broomfield. Please see the original public notice here. Extraction’s subcontractor, Lone Tree, is working under the Broomfield issued grading permit, doing the work required to complete the access drive, and at the same time moving dirt and beginning construction of the pad. Both activities need to be done simultaneously. Due to constraint of the site, soils on the site will need to be stockpiled as the access drive construction is accomplished. Stockpiled soils will then be used for the pad construction. As previously mentioned in the original public notice, construction is expected to continue through March and into April.