136th Avenue Turn Lanes at Legacy High School

136 Turn Lane 7-2021

News and Updates.....

The asphalt milling and paving work for the W. 136th Ave Safety Improvements at Legacy High School, which was scheduled to start July 16, has been delayed due to a regional asphalt supply shortage.  At this time, new milling and paving dates for this project are unknown.  This web page will be updated once the new milling and paving dates have been determined.  

Once paving does begin, the traveling public can expect delays and periodic/temporary closures of W. 136th Ave. from Westlake Dr. to W. 138th Ave. Detours will be in place for the periodic/temporary closures.  Please see the detour map below.  

We appreciate everyone's patience and understanding while we strive to complete this work. 

136th Work Zone at Legacy High School and Zuni St Map

Concrete Express, Inc. commenced construction on June 1, 2021.  The contractor has completed the install of new concrete curb, gutter and sidewalk as well as the relocation of existing inlet structures.  Paving work is delayed due to a regional asphalt shortage.  Landscape and irrigation work is continuing and is anticipated to be complete in early August 2021.  Construction is anticipated to be complete by mid-August 2021, prior to the start of the 2021-2022 school year.  

136th Turn Lanes July 2021