Quail Creek Channel - Westlake Lateral Drainage Improvements

NEWS AND UPDATES...

Work is continuing on the Diversion Structure on the east end of the project.  GoodLand poured the concrete floor for the manhole on Friday, October 30th.

During the week of November 2, 2020,  GoodLand will continue work on the Diversion Structure including additional concrete pours for the manhole and headwalls.  GoodLand will also pour the concrete top at the manhole on the west end of the project as well as the sidewalk adjacent to this manhole.  

Construction is currently on schedule and anticipated to be complete in November 2020.

Quail Creek Oct 30 2020Quail Creek Oct 16 2020 2

Quail Creek Oct 16 2020

Quail Creek Channel Oct 2020Quail Creek Channel Oct 2020 2

Quail Creek Oct 2 2020
Quail Creek 9-11-20